Earthworks Appear at Tesla's $10.1 Billion Texas Solar Factory
Nov. 9 footage showed earthworks at Tesla's proposed $10.1 billion solar plant near Houston. Has Tesla issued a formal groundbreaking notice?
Published Updated 3 min read

Site preparation and earthworks appeared on November 9, 2026, at Tesla's proposed Project Crystal Sun solar manufacturing site in Fort Bend County, inside Lamar CISD and southwest of Houston. S.E. Robinson, Jr. said he visited the property the day before and shared aerial footage of large clearings, equipment staging and land being leveled. Elon Musk then quoted Sawyer Merritt's X post and wrote only "Project Crystal Sun." Tesla has not issued a formal groundbreaking announcement.
Sawyer Merritt described the work as the official start of construction on the solar manufacturing facility near Houston. The images show real activity on the proposed site. However, they do not prove that every approval is complete or that Tesla has locked in the location in a company statement.

How big is Project Crystal Sun?
In the JETI application posted by the Texas Comptroller, Tesla put the investment at about $10.1 billion. About $1.5 billion would go to buildings and site improvements, and about $8.6 billion to production equipment. The plant would occupy portions of five parcels near FM 762 and FM 1994, on about 3,050 acres, or roughly 1,230 hectares.
The filing says the facility would make photovoltaic solar cells and assembled modules. Tesla described a vertically integrated line, from silicon ingots and wafers through cell production and finished panels. For example, most U.S. solar plants often assemble modules from imported cells, so this would be a fuller supply chain.
When could production begin?
According to the application, construction is expected to start in 2026 and finish in 2028, with commercial production targeted for the first quarter of 2029. However, the November 9 site images do not confirm that timetable on their own, and they also do not replace a formal Tesla statement.
TechCrunch reported on August 12, 2026 that the site is about 45 minutes southwest of Houston. Therefore the application does not disclose an annual capacity figure in gigawatts.
How many jobs could it create?
Tesla's filing projects 9,712 permanent full-time jobs at full capacity in 2033. However, that is not the opening headcount. The same schedule also shows 1,942 workers in 2029, the first year of operations, with the total rising in stages after that. Peak construction employment is listed at about 1,147 temporary jobs in 2028.
What do the economic estimates say?
Kroll's analysis attached to the filing estimates about $107 billion in Texas GDP impact over a 38-year period, and roughly $6.4 billion in combined state and local tax impact. Still, those figures are consultant projections in the incentive package, not findings from the drone video.
Tesla also wrote that it was evaluating sites in multiple U.S. states. In addition, local incentive approvals from Lamar CISD and Fort Bend County later in 2026 are part of that background. The visible site work is therefore a concrete step, not a formal groundbreaking notice from Tesla.
Meanwhile, this plan is about large-scale cell and panel manufacturing, not residential roof tiles. Tesla has already pushed solar as a way to power electric driving.
The company's energy business has also been a growing part of its story, alongside the car side of the brand.
Technical snapshot
| Item | Detail |
|---|---|
| Project name | Project Crystal Sun |
| Location | Fort Bend County, Lamar CISD, southwest of Houston |
| Investment | About $10.1 billion |
| Construction target | Start in 2026, finish in 2028 |
| Production target | First quarter of 2029 |
| Permanent jobs | 9,712 at full capacity in 2033 |
| Product | Photovoltaic solar cells and panels |